01

EVM Analysis

Start: 2025-12-01Welding MS: 2026-05-31Float: -70dEOT: 20%HIGH RISK
Time Elapsed
44.5%
94 of 211 days
Work Complete
3.1%
Overall progress
SPI
0.070
Schedule Performance
CPI
0.199
Cost Performance
Cost to Date
$658,718
incl. Samsung BC: $776,300
EAC
$13,830,861
403% overrun
01

Earned Value Management (EVM)

Performance indices and cost/schedule variance as of 2026-03-05 · Budget: $2,747,253

Editable Inputs

3.1%
10,000,000
1,597,732
800,000
Planned Value
$1,880,323
USD
Earned Value
$130,842
USD
Actual Cost
$658,718
USD
SPI
0.070
CRITICAL
CPI
0.199
CRITICAL
EAC
$13.83M
403% overrun
EVM MetricValue (USD)Implication
Budget at Completion (BAC)$2,747,253Original contract budget (QAR 10M / 3.64 rate)
Planned Value (PV)$1,880,323Value of work planned by 2026-03-05
Earned Value (EV)$130,8423.1% of scope completed
Actual Cost (AC)$658,718Total cost incurred to date
Schedule Variance (SV)$-1,749,480Negative = behind schedule
Cost Variance (CV)$-527,875Negative = over budget
SPI0.0696<1.0 = behind schedule
CPI0.1986<1.0 = over budget
Estimate at Completion (EAC)$13,830,861Projected final cost (CPI-based)
Estimate to Complete (ETC)$13,172,144Remaining cost to finish
Variance at Completion (VAC)$-11,083,608Projected budget surplus/(deficit)

EVM S-Curve — Planned Value / Planned Cost / Actual Cost / Earned Value (USD)

Planned Value (Work) = value of work scheduled · Planned Cost (Budget) = budgeted spend profile (sums to $2,747,253) · Actual Cost = money spent · Earned Value = value of work done

2025-122025-122026-012026-012026-022026-022026-032026-032026-032026-042026-042026-052026-052026-062026-062026-06$0K$700K$1400K$2100K$2800KToday
  • Planned Value (Work)
  • Planned Cost (Budget)
  • Actual Cost
  • Earned Value